Status

Pre-stage

Task Maintainer Workload State Remarks
Base setup wyo ~ 2-4 weeks first version
wxGDK port wyo 12 month(?) -
Check DirectFB wyo 2 month(?) 0.1.beta Checks framebuffer and DirectFB

Stage 1

Task Maintainer Workload State Remarks
Desktop manager - 12 month(?) -
Login application wyo 2 month(?) First version Checks for the correct password
Control center - 2 month(?) -
wyoFiler wyo +4 month 0.7.2
Menu application - 2 month(?) -
Shell/terminal - 2 month(?) -

Stage 2

Task Maintainer Workload State Remarks
Help viewer - 2 month(?) Concept drafted
Mimetype library - 8 month(?) Concept drafted
Linux bundle files - 6 month(?) Concept drafted
Trashcan concept - 6 month(?) -

Stage 3

Task Maintainer Workload State Remarks
GTK application integration - 4 month(?) -
QT application integration - 4 month(?) -
X application integration - 4 month(?) -

To do